| Installation of heat lamps, Pershing Square West Plaza, Park Avenue between East 41st Street and East 42nd Street, Manhattan |
Manhattan |
DDC |
Building systems & Modifications |
|
Commented |
2017-10-16 |
| 520 Park Avenue planters |
Manhattan |
DOT |
Street furniture |
|
Commented |
2017-10-16 |
| Installation of stabilization devices on a pedestrian bridge over Furman Street between Squibb Park and Brooklyn Bridge Park, Brooklyn |
Brooklyn |
BBP |
Bridge |
|
Commented |
2017-10-16 |
| Installation of rooftop mechanical equipment, Engine Company 323, 6405 Avenue N, Brooklyn |
Brooklyn |
FDNY |
Building systems & Modifications |
|
Commented |
2017-10-16 |
| Installation of rooftop mechanical equipment, Engine Company 22, 185 East 85th Street, Manhattan |
Manhattan |
FDNY |
Building systems & Modifications |
|
Commented |
2017-10-16 |
| Installation of rooftop mechanical equipment, Engine Company 321, 2165 Gerritsen Avenue, Brooklyn |
Brooklyn |
FDNY |
Building systems & Modifications |
|
Commented |
2017-10-16 |
| Installation of rooftop mechanical equipment, Engine Company 154, 3730 Victory Boulevard, Staten Island |
Staten Island |
FDNY |
Building systems & Modifications |
|
Commented |
2017-10-16 |
| Installation of a distinctive sidewalk, The Paramount Building, 1501 Broadway, 43rd street, between Broadway and 8th Avenue, Manhattan |
Manhattan |
DOT |
Distinctive sidewalk |
|
Approved |
2017-10-16 |
| Installation of a prototypical newsstand, 1332 Metropolitan Avenue, northeast corner of Metropolitan Avenue and Benedict Avenue, Bronx |
Bronx |
DCA |
Newsstand |
|
Commented |
2017-10-16 |
| Construction of a plaza and adjacent site work, Newtown Playground, 56th Avenue and 92nd Street, Elmhurst, Queens |
Queens |
DPR |
Landscape architecture |
|
Approved |
2017-10-16 |
| Reconstruction of the comfort station as Phase III of the reconstruction of Gravesend Park, 55th Street, 18th Avenue, 58th Street and 19th Avenue, Brooklyn |
Brooklyn |
DPR |
Architecture |
|
Commented |
2017-10-16 |
| Reconstruction of docks, Mill Basin Marina, East 69th Street and Avenue Y, Brooklyn |
Brooklyn |
DPR |
Architecture |
|
Approved |
2017-10-16 |
| Reconstruction of athletic courts and installation of an artificial turf field, General Douglas MacArthur Park, Dongan Hills Avenue and Jefferson Street, Staten Island |
Staten Island |
DPR |
Landscape architecture |
|
Approved |
2017-10-16 |
| Reconstruction of athletic fields and adjacent site work as Phase I of the reconstruction of Astoria Park, Astoria Park South, 21st Street, and Shore Boulevard, Astoria, Queens |
Queens |
DPR |
Landscape architecture |
|
Approved |
2017-10-16 |
| Reconstruction of Hallets Cove Playground, Vernon Boulevard between Welling Court and 30th Road, Astoria, Queens |
Queens |
DPR |
Landscape architecture |
|
Approved |
2017-10-16 |
| Reconstruction of the East River Esplanade, East 68th Street to East 70th Street, Manhattan |
Manhattan |
DPR |
Landscape architecture |
|
Approved |
2017-10-16 |
| Reconstruction of a portion of Park Slope Playground including green infrastructure, adjacent to P. S. 282, Lincoln Place, 6th Avenue, Berkeley Place, and 5th Avenue, Brooklyn |
Brooklyn |
DEP |
Landscape architecture |
|
Approved |
2017-10-16 |
| Installation of interim flood protection measures, Mason Avenue Pumping Station, 494 Mason Avenue, Staten Island |
Staten Island |
NYCEM |
Building systems & Modifications |
|
Commented |
2017-09-18 |
| Installation of a plaque, Sheldon Avenue Bluebelt, Sweet Brook watershed, Staten Island |
Staten Island |
DDC |
Signage |
|
Commented |
2017-09-18 |
| Rehabilitation of the Shaft 9 gatehouse and adjacent site work, New Croton Aqueduct, Sleepy Hollow, Westchester County |
Upstate |
DEP |
Architecture |
|
Commented |
2017-09-18 |
| Rehabilitation of the Shaft 11A headhouse and adjacent site work, New Croton Aqueduct, White Plains Road, Greenburgh, Westchester County |
Upstate |
DEP |
Architecture |
|
Commented |
2017-09-18 |
| Rehabilitation of the Shaft 18 gatehouse and adjacent site work, New Croton Aqueduct, Yonkers Avenue, Yonkers, Westchester County |
Upstate |
DEP |
Architecture |
|
Commented |
2017-09-18 |
| Rehabilitation of the Shaft 23 headhouse and adjacent site work, New Croton Aqueduct, West Burnside Avenue, University Heights |
Upstate |
DEP |
Architecture |
|
Commented |
2017-09-18 |
| Rehabilitation of the Shaft 25 headhouse and adjacent site work, New Croton Aqueduct, Highbridge Park |
Upstate |
DEP |
Architecture |
|
Commented |
2017-09-18 |
| Reconstruction of a playground, Success Academy Charter School, P.S. 175, 175 West 134th Street, Manhattan |
Manhattan |
DOE |
Landscape architecture |
|
Approved |
2017-09-18 |
| Construction of an electrical building and adjacent site work, Oakwood Beach Water Pollution Control Plant, 751 Mill Road, Staten Island |
Staten Island |
DEP |
Architecture |
|
Approved |
2017-09-18 |
| Installation of artworks by Pablo Helguera, Far Rockaway Community Library, 16-37 Central Avenue, Far Rockaway, Queens |
Queens |
DCLA% |
Artwork |
|
Approved with conditions |
2017-09-18 |
| Construction of a covered artificial turf field and comfort station (FC Harlem), adjacent to the North River Wastewater Treatment Plant and Riverbank State Park, West 145th Street and the Henry Hudson Parkway, Manhattan |
Manhattan |
DEP |
Architecture |
|
Commented |
2017-09-18 |
| Construction of a utility shed, Glendale Yard, 69-46 Sybilla Street, Forest Hills, Queens |
Queens |
DOT |
Architecture |
|
Approved with conditions |
2017-09-18 |
| Reconstruction of Public School 269 (Nostrand) Playground, southeast corner of Nostrand Avenue and Foster Avenue |
Upstate |
DPR |
Landscape architecture |
|
Commented |
2017-09-18 |
| Construction of a tennis stadium (Court 17), Billie Jean King National Tennis Center, Flushing Meadows Corona Park, Queens |
Queens |
DPR |
Architecture |
|
Commented |
2017-09-18 |
| Restoration of the 96th Street Branch Library, 112 East 96th Street, Manhattan |
Manhattan |
DDC |
Architecture |
|
Commented |
2017-09-18 |
| Construction of an adult fitness area and a basketball court, Bronx Park, Bronx River Parkway, Boston Road and Sagamore Street, Bronx |
Bronx |
DPR |
Landscape architecture |
|
Commented |
2017-09-18 |
| Construction of the Clearview Pumping Station, Clearview Expressway exit ramp, Roe Place and the Cross Island Parkway service road, Queens |
Queens |
DEP |
Architecture |
|
Commented |
2017-09-18 |
| Installation of a prototypical newsstand, 22-15 31st Street, southeast corner of 31st Street and Ditmars Boulevard, Astoria, Queens |
Queens |
DCA |
Newsstand |
|
Approved |
2017-09-18 |
| Reconstruction of an entrance, Bushwick Communicare Health Center, 335 Central Avenue, Brooklyn |
Brooklyn |
DDC |
Architecture |
|
Commented |
2017-09-18 |
| Installation of a pre-fabricated storage building, Prospect Park, Prospect Park West between Sixth Street and Eighth Street, Brooklyn |
Brooklyn |
DPR |
Architecture |
|
Approved |
2017-09-18 |
| Reconstruction of a picnic area, Prospect Park Picnic House, Prospect Park West and Fifth Street, Brooklyn |
Brooklyn |
DPR |
Landscape architecture |
|
Approved |
2017-09-18 |
| Reconstruction of the picnic areas and adjacent site work, Prospect Park Bandshell, Prospect Park West between 9th Street and 11th Street, Brooklyn |
Brooklyn |
DPR |
Landscape architecture |
|
Approved |
2017-09-18 |
| Installation of a rooftop exhaust fan, Essex Street Market, 120 Essex Street at Delancey Street, Manhattan |
Manhattan |
EDC |
Building systems & Modifications |
|
Approved |
2017-09-18 |
| Reconstruction of the New York City Police Substation (formerly Times Square Sweep-up Booth, formerly Times Square Information Booth), Broadway and 43rd Street, 43rd Street between Broadway and 7th Avenue, Manhattan |
Manhattan |
NYPD |
Architecture |
|
Approved |
2017-09-18 |
| 108 Leonard Street, Leonard Street between Lafayette and Broadway, Distinctive Lighting |
Manhattan |
DOT |
Distinctive lighting |
|
Commented |
2017-09-18 |
| Installation of a distinctive sidewalk, Inter-Continental Hotel- The Barclay New York, 111 East 48th Street, between Park Avenue and Lexington Avenue, Manhattan |
Manhattan |
DOT |
Distinctive sidewalk |
|
Commented |
2017-09-18 |
| Installation of windows and a curtain wall, 111 Precinct, 45-06 21 5th Street, Bayside, Queens |
Queens |
DDC |
Building systems & Modifications |
|
Commented |
2017-09-18 |
| Update to the design of a master plan for the reconstruction of Sherman Creek Park, including the construction of a boat storage building, outdoor pavilion, and adjacent site work, Tenth Avenue, Harlem River Drive, Academy Street, and Sherman Creek, Manhattan |
Manhattan |
DPR |
Landscape architecture |
|
Commented |
2017-09-18 |
| Construction of the Edenwald YMCA facility and adjacent site work, Christopher School Facility, 1250 East 229th Street at Schieffelin Place, Bronx |
Bronx |
EDC |
Architecture |
|
Approved |
2017-09-18 |
| Installation of a prototypical newsstand, 617 Pacific Street, southwest corner of Flatbush Avenue and Atlantic Avenue, Brooklyn |
Brooklyn |
DCA |
Newsstand |
|
Approved with conditions |
2017-09-18 |
| Installation of a sealcoat soccer field, P.S./ I.S. 66, 845 East 96th Street, Brooklyn |
Brooklyn |
DOE |
Landscape architecture |
|
Approved |
2017-09-18 |
| Installation of an artificial turf field and basketball courts, P.S. 43, Jonas Bronck School, 165 Brown Place, Bronx |
Bronx |
DOE |
Landscape architecture |
|
Approved |
2017-09-18 |
| Construction of the Queens Vietnam Veterans Memorial, Elmhurst Park, Grand Avenue and 79th Street, Elmhurst, Queens |
Queens |
DPR |
Landscape architecture |
|
Approved |
2017-09-18 |