Reconstruction of the New York City Police Substation (formerly Times Square Sweep-up Booth, formerly Times Square Information Booth), Broadway and 43rd Street, 43rd Street between Broadway and 7th Avenue, Manhattan

Manhattan · NYPD · Architecture · Final · Approved

City Council
3
Community Board
5
Construction
Reconstruction
Public/Private
Public
Review Cycles
1
First Seen
2017-09-18
Last Seen
2017-09-18

Stage Progression

Conceptual
Preliminary
2017-07-17
Final
2017-09-18
Preliminary → Final: 63 days

Review History

DateCertificateStageActionResultSourceDocs
2017-09-18 26407 Final agenda_pdf Minutes
2017-09-18 Approved annual_report_api Minutes