Reconstruction of the comfort station as Phase III of the reconstruction of Gravesend Park, 55th Street, 18th Avenue, 58th Street and 19th Avenue, Brooklyn

Brooklyn · DPR · Architecture · Final · Commented

Construction
Reconstruction
Public/Private
Public
First Seen
2017-10-16
Last Seen
2017-10-16

Stage Progression

Conceptual
Preliminary
2013-06-03
Final
2014-05-19
Preliminary → Final: 350 days
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2017-10-16 Commented annual_report_api Minutes