Construction of a maintenance building, a comfort station, and adjacent site work, as Phase II and Phase III of the construction of a waterfront park and streetscape improvements, Thompson Street, Wave Street and Bay Street, Stapleton, Staten Island

Staten Island · EDC · Architecture · Final · Approved

City Council
49
Community Board
1
Construction
Construction
Public/Private
Public
Review Cycles
2
First Seen
2020-04-20
Last Seen
2020-04-20

Stage Progression

Conceptual
Preliminary
2020-04-20
Final
2022-07-11
Preliminary → Final: 812 days

Review History

DateCertificateStageActionResultSourceDocs
2020-03-30 Commented annual_report_api Minutes
2020-04-20 27469 Preliminary agenda_pdf Minutes
2020-04-20 Approved annual_report_api Minutes
2020-04-20 27469 Preliminary Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission's Commission Meeting April 20, 2020 (2020-04-20)
Public Design Commission Meeting March 30, 2020 (2020-03-30)

Related Projects

Same project, different review stage (2)
TitleStageFirst SeenLast Seen
Construction of a maintenance building, a comfort station, and adjacent site wor… 2019-07-15 2019-09-16
Construction of a maintenance building, a comfort station, and adjacent site wor… Final 2022-07-11 2022-07-11
Modifications (1)
TitleStageFirst SeenResult
Minor modifications to a retaining wall as part of the construction of a mainten… Amended Final 2024-09-16 Approved