Construction of a maintenance building, a comfort station, and adjacent site work, as Phase II and Phase III of the construction of a waterfront park and streetscape improvements, Thompson Street, Wave Street and Bay Street, Stapleton, Staten Island

Staten Island · EDC · Architecture · Approved

City Council
49
Community Board
1
Construction
Construction
Public/Private
Public
Review Cycles
2
First Seen
2020-04-20
Last Seen
2020-04-20

Stage Progression

Conceptual
Preliminary
2020-04-20
Final

Review History

DateCertificateStageActionResultSourceDocs
2020-03-30 Commented annual_report_api Minutes
2020-04-20 27469 Preliminary agenda_pdf Minutes
2020-04-20 Approved annual_report_api Minutes
2020-04-20 27469 Preliminary Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Meeting March 30, 2020 (2020-03-30)