Construction of a maintenance building, a comfort station, and adjacent site work, as Phase II and Phase III of the construction of a waterfront park and streetscape improvements, Thompson Street, Wave Street and Bay Street, Stapleton, Staten Island

Staten Island · EDC · Architecture · Final · Approved

Construction
Construction
Public/Private
Public
First Seen
2019-07-15
Last Seen
2019-09-16

Stage Progression

Conceptual
Preliminary
2020-04-20
Final
2022-07-11
Preliminary → Final: 812 days

Review History

DateCertificateStageActionResultSourceDocs
2019-07-15 Commented annual_report_api Minutes
2019-08-12 Commented annual_report_api Minutes
2019-09-16 Commented annual_report_api Minutes

Related Projects

Same project, different review stage (2)
TitleStageFirst SeenLast Seen
Construction of a maintenance building, a comfort station, and adjacent site wor… Preliminary 2020-04-20 2020-04-20
Construction of a maintenance building, a comfort station, and adjacent site wor… Final 2022-07-11 2022-07-11
Other projects at this site (1)
TitleStageAgencyFirst Seen
Minor modifications to a retaining wall as part of the construction of a mainten… Amended Final EDC 2024-09-16