Construction of a comfort station and adjacent site work, Owl Hollow Fields, Arthur Kill Road, Route 440 and Arden Avenue, Staten Island

Staten Island · DPR · Architecture · Commented

Construction
Construction
Public/Private
Public
First Seen
2019-02-19
Last Seen
2020-05-18

Stage Progression

Conceptual
Preliminary
Final

Review History

DateCertificateStageActionResultSourceDocs
2019-02-19 Commented annual_report_api Minutes
2019-03-18 Commented annual_report_api Minutes
2019-04-15 Commented annual_report_api Minutes
2020-04-20 Commented annual_report_api Minutes
2020-05-18 Commented annual_report_api Minutes

Meeting Videos

Public Design Commission Meeting Agenda Monday, May 18, 2020 (2020-05-18)
Public Design Commission's Commission Meeting April 20, 2020 (2020-04-20)
Subscribe to Updates Back to Projects