Construction of a café storage space, Hunter's Point South Park, Center Boulevard at Borden Avenue, Long Island City, Queens Queens DPR Approved Agenda
Minutes
Construction of a café storage space, Hunter's Point South Park, Center Boulevard at Borden Avenue, Long Island City, Queens Queens DPR Preliminary Agenda
Minutes
Construction of a community center (Brownsville Girls Empowerment Center and Community Hub), 444 Thomas S Boyland Street between East New York Avenue and Pitkin Avenue, Brooklyn Brooklyn DDC Commented Agenda
Minutes
Construction of a modular compost facility office, Greenpoint Marine Transfer Station, Newtown Creek at Kingsland Avenue, Brooklyn Brooklyn DSNY Approved Agenda
Minutes
Construction of a modular compost facility office, Greenpoint Marine Transfer Station, Newtown Creek at Kingsland Avenue, Brooklyn Brooklyn DSNY Preliminary Agenda
Minutes
Construction of an off-shore wind operations and maintenance building and adjacent sitework, South Brooklyn Marine Terminal, 2nd Avenue between 32nd Street and 34th Street, Brooklyn Brooklyn EDC Commented Agenda
Minutes
Construction of a parking lot for the 32nd Precinct, 2510 Frederick Douglass Boulevard and 271 West 134th Street, Manhattan Manhattan NYPD Approved Agenda
Minutes
Construction of a parking lot for the 32nd Precinct, 2510 Frederick Douglass Boulevard and 271 West 134th Street, Manhattan Manhattan NYPD Preliminary and Final Agenda
Minutes
Construction of a performance space and shade structure, Rockaway Beach, Shore Front Parkway between Beach 94th Street and Beach 95th Street, Far Rockaway, Queens Queens DPR Commented Agenda
Minutes
Construction of a recreation center (Shirley Chisholm Recreation Center) and adjacent site work, 3002 Foster Avenue between Nostrand Avenue and New York Avenue, Brooklyn Brooklyn DDC Approved with conditions Agenda
Minutes
Construction of a recreation center (Shirley Chisholm Recreation Center) and adjacent site work, 3002 Foster Avenue between Nostrand Avenue and New York Avenue, Brooklyn Brooklyn DDC Preliminary Agenda
Minutes
Construction of a residential building, streetscape, and plazas, 126th Street and Roosevelt Avenue, Willets Point, Corona, Queens Queens EDC Final Agenda
Minutes
Construction of a residential building, streetscape, and plazas, 126th Street and Roosevelt Avenue, Willets Point, Corona, Queens Queens EDC Approved Agenda
Minutes
Construction of a skate park and adjacent site work, Power Playground, Avenue N, Utica Avenue, Avenue O, and East 49th Street, Brooklyn Brooklyn DPR Final Agenda
Minutes
Construction of a skate park and adjacent site work, Power Playground, Avenue N, Utica Avenue, Avenue O, and East 49th Street, Brooklyn Brooklyn DPR Approved Agenda
Minutes
Construction of bridges over West 203rd Street connecting two Con Edison buildings, 3775 Ninth Avenue and 3795 Ninth Avenue, Manhattan Manhattan DOT Commented Agenda
Minutes
Construction of interim trailers, Newtown High School Athletic Field, northeast corner of 57th Avenue and 90th Street, 90-02 56th Avenue, Elmhurst, Queens Queens FDNY Approved Agenda
Minutes
Construction of interim trailers, Newtown High School Athletic Field, northeast corner of 57th Avenue and 90th Street, 90-02 56th Avenue, Elmhurst, Queens Queens FDNY Preliminary and Final Agenda
Minutes
Construction of streetscape improvements, including an El-Fence, Sutter Avenue between Van Sinderen Avenue and Hinsdale Street, and Van Sinderen Avenue between East New York Avenue and Riverdale Avenue, Brooklyn Brooklyn DDC Preliminary Agenda
Minutes
Construction of streetscape improvements, including an El-Fence, Sutter Avenue between Van Sinderen Avenue and Hinsdale Street, and Van Sinderen Avenue between East New York Avenue and Riverdale Avenue, Brooklyn Brooklyn DDC Approved Agenda
Minutes
Design of a mixed-use development, including a stadium, as part of Phase II of Willets Point, 126th Street and 127th Street between Northern Boulevard, Willets Point Boulevard and Roosevelt Avenue, Corona, Queens Queens EDC Commented Agenda
Minutes
Design of a wayfinding and environmental graphics system, Brooklyn Navy Yard Industrial Park, Brooklyn Brooklyn BNYDC Approved with conditions Agenda
Minutes
Design of a wayfinding and environmental graphics system, Brooklyn Navy Yard Industrial Park, Brooklyn Brooklyn BNYDC Final Agenda
Minutes
Design of prototypical bus shelters for installation on narrow sidewalks citywide Citywide DOT Withdrawn Agenda
Minutes
Design of tree guards as part of the reconstruction of Union Square, Union Square Partnership BID District, Sixth Avenue, First Avenue, 13th Street and 18th Street, Manhattan Manhattan DPR Approved Agenda
Minutes
Design of tree guards as part of the reconstruction of Union Square, Union Square Partnership BID District, Sixth Avenue, First Avenue, 13th Street and 18th Street, Manhattan Manhattan DPR Preliminary and Final Agenda
Minutes
Extension for the temporary installation of Fearless Girl by Kristen Visbal, Broad Street between Wall Street and Exchange Place, Manhattan Manhattan DOT Withdrawn Agenda
Minutes
Installation of a distinctive sidewalk and lighting, 292 Kent Avenue (Domino Sugar Refinery) and 320 Kent Avenue, Brooklyn Brooklyn DOT Commented Agenda
Minutes
Installation of a manhole and piping, Engine Company 52/Ladder Company 52, 4550 Henry Hudson Parkway East, Bronx Bronx FDNY Approved per delegation Agenda
Minutes
Installation of a modular comfort station and adjacent site work, Discovery Playground, Fort Washington Park, Henry Hudson Parkway near West 163rd Street, Manhattan Manhattan DPR Final Agenda
Minutes
Installation of a modular comfort station and adjacent site work, Discovery Playground, Fort Washington Park, Henry Hudson Parkway near West 163rd Street, Manhattan Manhattan DPR Approved Agenda
Minutes
Installation of a rooftop flue, Kenton Hall men's shelter, 333 Bowery, Manhattan Manhattan DHS Approved per delegation Agenda
Minutes
Installation of a storage tank, Fulton Fish Market at Hunts Point Market, 800 Food Center Drive, Bronx Bronx EDC Preliminary and Final Agenda
Minutes
Installation of a storage tank, Fulton Fish Market at Hunts Point Market, 800 Food Center Drive, Bronx Bronx EDC Approved Agenda
Minutes
Installation of distinctive lighting as part of the construction of a parking garage and community facility as part of the Borough-Based Jails Program, Union Turnpike between 126th Street and 132nd Street, Kew Gardens, Queens Queens DDC Approved Agenda
Minutes
Installation of distinctive lighting as part of the construction of a parking garage and community facility as part of the Borough-Based Jails Program, Union Turnpike between 126th Street and 132nd Street, Kew Gardens, Queens Queens DDC Amended Final Agenda
Minutes
Installation of gas line, meter and piping, Operations Office, Sara D. Roosevelt Park, 263 Grand Street between Chrystie Street, Forsyth Street, and Delancey Street, Manhattan Manhattan DDC Commented Agenda
Minutes
Installation of mechanical enclosures and reconstruction of a roof, Bushwick Branch Library, 340 Bushwick Avenue, Brooklyn Brooklyn DDC Commented Agenda
Minutes
Installation of rooftop equipment, Sewage Treatment Worker Locker Room, Pump and Blower Building, Tallman Island Wastewater Resource Recovery Facility, 127th Street and Powell's Cove Boulevard, College Point, Queens Queens DEP Approved per delegation Agenda
Minutes
Installation of rooftop mechanical equipment, 104th Precinct, 6402 Catalpa Avenue, Ridgewood, Queens Queens NYPD Approved per delegation Agenda
Minutes
Installation of rooftop mechanical equipment, Asphalt Green Recreation Center, 1750 York Avenue, Manhattan Manhattan DPR Commented Agenda
Minutes
Installation of rooftop photovoltaic panels, Elmhurst Hospital Center, 79-01 Broadway, Elmhurst, Queens Queens DCAS Approved per delegation Agenda
Minutes
Installation of rooftop photovoltaic panels, Engine Company 257/Ladder Company 170, 1361 Rockaway Pkwy, Brooklyn Brooklyn FDNY Approved per delegation Agenda
Minutes
Installation of rooftop photovoltaic panels, Engine Company 66/Ladder company 61, 21 Asch Loop, Bronx Bronx FDNY Approved per delegation Agenda
Minutes
Installation of rooftop photovoltaic panels, Engine Company 81/Ladder Company 46, 3025 Bailey Avenue, Bronx Bronx FDNY Approved per delegation Agenda
Minutes
Installation of rooftop photovoltaic panels, K206, 2200 Avenue V, Brooklyn Brooklyn DCAS Approved per delegation Agenda
Minutes
Installation of rooftop photovoltaic panels, M028, 453 West 155th Street, Manhattan Manhattan DCAS Approved per delegation Agenda
Minutes
Installation of rooftop photovoltaic panels, Q205, 75-25 Bell Boulevard, Queens Queens DCAS Approved per delegation Agenda
Minutes
Installation of rooftop photovoltaic panels, X140, 916 Eagle Avenue, Bronx Bronx DCAS Approved per delegation Agenda
Minutes
Installation of signage (2 Bridge Mall), 75 East Broadway, Manhattan Manhattan EDC Approved per delegation Agenda
Minutes
Installation of signage at a ballpark (Staten Island University Hospital Northwell Health Community Park), 75 Richmond Terrace, north of the Staten Island Ferry Terminal, Staten Island Staten Island EDC Approved Agenda
Minutes
Installation of signage at a ballpark (Staten Island University Hospital Northwell Health Community Park), 75 Richmond Terrace, north of the Staten Island Ferry Terminal, Staten Island Staten Island EDC Preliminary and Final Agenda
Minutes
Installation of signage (Universal Hip Hop Museum), Bronx Point, Major Deegan Expressway, 145th Street Bridge, East 150th Street, and the Harlem River, Bronx Bronx EDC Commented Agenda
Minutes
Installation of vent stacks and an electrical meter, Canal Street Pump Station, Canal Street between Varick Street and the Avenue of the Americas, Manhattan Manhattan DEP Approved Agenda
Minutes
Installation of vent stacks and an electrical meter, Canal Street Pump Station, Canal Street between Varick Street and the Avenue of the Americas, Manhattan Manhattan DEP Preliminary and Final Agenda
Minutes
Minor modifications to the construction of a parking lot adjacent to Building 280, Flushing Avenue, North Oxford Street, Ordinance Avenue, and Fifth Street, Brooklyn Navy Yard Industrial Park, Brooklyn Brooklyn BNYDC Approved per delegation Agenda
Minutes
Minor modifications to the reconstruction of an asphalt plant, including construction of an interim administration building, and adjacent site work, Harper Street Yard, 30-01 Harper Street, Corona, Queens Queens DDC Amended Final Agenda
Minutes
Minor modifications to the reconstruction of an asphalt plant, including construction of an interim administration building, and adjacent site work, Harper Street Yard, 30-01 Harper Street, Corona, Queens Queens DDC Approved Agenda
Minutes
Minor modifications to the rehabilitation of the Bushwick Health Center, 335 Central Avenue, Brooklyn Brooklyn DDC Approved Agenda
Minutes
Minor modifications to the rehabilitation of the Bushwick Health Center, 335 Central Avenue, Brooklyn Brooklyn DDC Amended Final Agenda
Minutes
Minor modifications to the renovation of a nature center and adjacent site work, West 218th Street and Indian Road, Inwood Hill Park, Manhattan Manhattan DPR Approved per delegation Agenda
Minutes
Minor modification to bollards as part of the construction of Plaza 33, including installation of a distinctive sidewalk, West 33rd Street at Seventh Avenue, Manhattan Manhattan DOT Amended Final Agenda
Minutes
Minor modification to bollards as part of the construction of Plaza 33, including installation of a distinctive sidewalk, West 33rd Street at Seventh Avenue, Manhattan Manhattan DOT Approved Agenda
Minutes
Minor modification to the installation of commemorative plaques and a flagpole, 239th Street median at Hillside Avenue, Bellerose, Queens Queens DOT Commented Agenda
Minutes
Reconstruction of a fueling station and installation of fuel tank access hatches, 77th Precinct Annex, 653 Grand Avenue, Brooklyn Brooklyn DDC Approved per delegation Agenda
Minutes
Reconstruction of an NYPD warehouse, 109 23rd Street, Gowanus Canal between 22nd Street and 23rd Street, Brooklyn Brooklyn NYPD Withdrawn Agenda
Minutes
Reconstruction of a plaza, performance space, pathways, and adjacent site work as Phase II of the reconstruction of St. Mary's Park, St. Ann’s Avenue, East 149th Street, Jackson Avenue, and St. Mary’s Street, Bronx Bronx DPR Commented Agenda
Minutes
Reconstruction of a storefront entryway, Arthur Avenue Retail Market, 2344 Arthur Avenue, Bronx Bronx EDC Approved per delegation Agenda
Minutes
Reconstruction of Callahan-Kelly Park, Broadway Junction, Van Sinderen Avenue, Truxton Street, Eastern Parkway, and Fulton Street, Brooklyn Brooklyn DPR Approved Agenda
Minutes
Reconstruction of Callahan-Kelly Park, Broadway Junction, Van Sinderen Avenue, Truxton Street, Eastern Parkway, and Fulton Street, Brooklyn Brooklyn DPR Amended Final Agenda
Minutes
Reconstruction of Dawson Playground, adjacent to P.S. 60, Dawson Street and Rogers Place, Bronx Bronx DPR Preliminary Agenda
Minutes
Reconstruction of Dawson Playground, adjacent to P.S. 60, Dawson Street and Rogers Place, Bronx Bronx DPR Approved Agenda
Minutes
Reconstruction of Honey Locust Park, 59th Street between First Avenue and Second Avenue, Manhattan Manhattan DPR Commented Agenda
Minutes
Reconstruction of Horace Harding Playground, adjacent to P.S. 206, 98th Street, 62nd Drive, and 97th Place, Rego Park, Queens Queens DPR Approved Agenda
Minutes
Reconstruction of Horace Harding Playground, adjacent to P.S. 206, 98th Street, 62nd Drive, and 97th Place, Rego Park, Queens Queens DPR Final Agenda
Minutes
Reconstruction of Lt. Lia Playground, St. Marks Place, Wall Street, and Belmont Place, Staten Island Staten Island DPR Preliminary Agenda
Minutes
Reconstruction of Lt. Lia Playground, St. Marks Place, Wall Street, and Belmont Place, Staten Island Staten Island DPR Approved Agenda
Minutes
Reconstruction of Marcy Green Park, Marcy Avenue between South 3rd Street and Broadway Avenue, Brooklyn Brooklyn DPR Commented Agenda
Minutes
Reconstruction of the Cumberland Street Gate and Clinton Avenue Gate, and adjacent site work, Flushing Avenue at Cumberland Street and Sixth Street, and at Clinton Avenue and Tenth Avenue, Brooklyn Navy Yard Industrial Park, Brooklyn Brooklyn BNYDC Final Agenda
Minutes
Reconstruction of the Cumberland Street Gate and Clinton Avenue Gate, and adjacent site work, Flushing Avenue at Cumberland Street and Sixth Street, and at Clinton Avenue and Tenth Avenue, Brooklyn Navy Yard Industrial Park, Brooklyn Brooklyn BNYDC Approved Agenda
Minutes
Reconstruction of the landscape to accommodate citywide ferry service, including the installation of electrical equipment, fencing and access gate, Bay Ridge-American Veterans Memorial Pier, Bay Ridge Avenue and New York Bay, Brooklyn Brooklyn EDC Commented Agenda
Minutes
Reconstruction of the landscape to accommodate citywide ferry service, including the installation of electrical equipment, fencing and access gate, Beach 108th Street and Beach Channel Drive, Queens Queens EDC Commented Agenda
Minutes
Reconstruction of the landscape to accommodate citywide ferry service, including the installation of electrical equipment, fencing and access gate, Hallets Cove, East River between Hallets Point Playground and Goodwill Park, Astoria, Queens Queens EDC Commented Agenda
Minutes
Reconstruction of the landscape to accommodate citywide ferry service, including the installation of electrical equipment, fencing and access gate, Pier 6, Brooklyn Bridge Park, Brooklyn Brooklyn EDC Commented Agenda
Minutes
Reconstruction of the Little Neck Pump Station, 40th Avenue and 248th Street, Little Neck, Queens Queens DEP Approved Agenda
Minutes
Reconstruction of the Little Neck Pump Station, 40th Avenue and 248th Street, Little Neck, Queens Queens DEP Preliminary and Final Agenda
Minutes
Reconstruction of the Lower Vale, Prospect Park, Flatbush Avenue between Grand Army Plaza and the Prospect Park Zoo, Brooklyn Brooklyn DPR Approved with conditions Agenda
Minutes
Reconstruction of the Lower Vale, Prospect Park, Flatbush Avenue between Grand Army Plaza and the Prospect Park Zoo, Brooklyn Brooklyn DPR Preliminary Agenda
Minutes
Reconstruction of the playground, St. Vartan Park, First Avenue, East 36th Street, Second Avenue, and East 35th Street, Manhattan Manhattan DPR Approved Agenda
Minutes
Reconstruction of the playground, St. Vartan Park, First Avenue, East 36th Street, Second Avenue, and East 35th Street, Manhattan Manhattan DPR Final Agenda
Minutes
Reconstruction of the Upper Vale, including construction of the Northeast Pavilion, Prospect Park, Flatbush Avenue between Grand Army Plaza and the Prospect Park Zoo, Brooklyn Brooklyn DPR Commented Agenda
Minutes
Reconstruction of William F. Moore Park, 108th Street, Corona Avenue, and 51st Avenue, Corona, Queens Queens DPR Approved Agenda
Minutes
Reconstruction of William F. Moore Park, 108th Street, Corona Avenue, and 51st Avenue, Corona, Queens Queens DPR Final Agenda
Minutes
Reconstruction of Zimmerman Playground, Barker Avenue, Britton Street, and Olinville Avenue, Bronx Bronx DPR Preliminary Agenda
Minutes
Reconstruction of Zimmerman Playground, Barker Avenue, Britton Street, and Olinville Avenue, Bronx Bronx DPR Approved with conditions Agenda
Minutes
Redesign of the Garment District Needle and Button sculpture, northeast corner of Seventh Avenue and 39th Street, Manhattan Manhattan DOT Commented Agenda
Minutes
Rehabilitation of a substation, Building 386, Dry Dock 5 at Assembly Road and Market Street, Brooklyn Navy Yard Industrial Park, Brooklyn Brooklyn BNYDC Approved Agenda
Minutes
Rehabilitation of a substation, Building 386, Dry Dock 5 at Assembly Road and Market Street, Brooklyn Navy Yard Industrial Park, Brooklyn Brooklyn BNYDC Preliminary and Final Agenda
Minutes
Rehabilitation of the Roy Wilkins Recreation Center, including replacement of the roof and adjacent site work, 177-01 Baisley Boulevard, Queens Queens DPR Commented Agenda
Minutes
Removal of a distinctive sidewalk, Metropolitan Recreation Center, 261 Bedford Avenue, Bedford Avenue between North 1st Street and Metropolitan Avenue, Brooklyn Brooklyn DPR Approved Agenda
Minutes
Removal of a distinctive sidewalk, Metropolitan Recreation Center, 261 Bedford Avenue, Bedford Avenue between North 1st Street and Metropolitan Avenue, Brooklyn Brooklyn DPR Preliminary and Final Agenda
Minutes
Repainting of the Northern Boulevard Bridges over the Flushing River, Flushing, Queens Queens DOT Approved Agenda
Minutes
Repainting of the Northern Boulevard Bridges over the Flushing River, Flushing, Queens Queens DOT Preliminary and Final Agenda
Minutes
Upgrade of the primary treatment system, including construction of a settling tank, a motor control center, a flow division structure, and interim grit building and adjacent site work, 26th Ward Wastewater Resource Recovery Facility, 12266 Flatlands Avenue, Brooklyn Brooklyn DEP Commented Agenda