Reconstruction of the Cumberland Street Gate and Clinton Avenue Gate, and adjacent site work, Flushing Avenue at Cumberland Street and Sixth Street, and at Clinton Avenue and Tenth Avenue, Brooklyn Navy Yard Industrial Park, Brooklyn

Brooklyn · BNYDC · Architecture · Final · Approved

Construction
Reconstruction
Public/Private
Public
Review Cycles
1
First Seen
2023-04-24
Last Seen
2023-04-24

Stage Progression

Conceptual
Preliminary
2022-10-11
Final
2023-04-24
Preliminary → Final: 195 days

Review History

DateCertificateStageActionResultSourceDocs
2023-04-24 Approved annual_report_api Minutes
2023-04-24 28426 Final Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Meeting, April 24, 2023 (2023-04-24)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Reconstruction of the Cumberland Street Gate and Clinton Avenue Gate, and adjace… Preliminary 2022-10-11 2022-10-11
Subscribe to Updates Back to Projects