Reconstruction of Horace Harding Playground, adjacent to P.S. 206, 98th Street, 62nd Drive, and 97th Place, Rego Park, Queens

Queens · DPR · Landscape architecture · Final · Approved

Construction
Reconstruction
Public/Private
Public
Review Cycles
1
First Seen
2023-04-24
Last Seen
2023-04-24

Stage Progression

Conceptual
Preliminary
2021-06-21
Final
2023-04-24
Preliminary → Final: 672 days

Review History

DateCertificateStageActionResultSourceDocs
2023-04-24 Approved annual_report_api Minutes
2023-04-24 28444 Final Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Meeting, April 24, 2023 (2023-04-24)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Reconstruction of Horace Harding Playground, adjacent to P.S. 206, 98th Street, … Preliminary 2021-06-21 2021-06-21