| Reconstruction of Forsyth Plaza, Canal Street, Forsyth Street and the Manhattan Bridge approach ramp, Manhattan |
Manhattan |
DDC |
Landscape architecture |
|
Commented |
2018-10-15 |
| Installation of rooftop photovoltaic panels, Bronx Elementary School 92, P.S. 352, 700 East 179th Street, Bronx |
Bronx |
DCAS |
Building systems & Modifications |
|
Commented |
2018-10-15 |
| Construction of a dechlorination facility, Owl's Head Water Pollution Control Plant, 6700 Shore Road, Brooklyn |
Brooklyn |
DEP |
Architecture |
|
Commented |
2018-10-15 |
| Installation of prototypical area wayfinding (WalkNYC) signs, East 61st Street and 5th Avenue, East 65th Street and 5th Avenue, East 72nd Street and 5th Avenue, East 84th Street and 5th Avenue, East 90th Street and 5th Avenue, Central Park North and Adam Clayton Powell Boulevard, West 109th Street and Central Park West, and West 60th and Central Park West, Central Park, Manhattan |
Manhattan |
DOT |
Street furniture |
|
Commented |
2018-10-15 |
| Installation of rooftop photovoltaic panels, I.S. 10, Horace Greeley Middle School, 45-11 31st Avenue, Long Island City, Queens |
Queens |
DCAS |
Building systems & Modifications |
|
Commented |
2018-10-15 |
| Installation of a prototypical newsstand, 237 East Fordham Road, northeast corner of Valentine Avenue and East Fordham Road, Bronx |
Bronx |
DCA |
Newsstand |
|
Commented |
2018-10-15 |
| Installation of rooftop photovoltaic panels, M.S. 582, 207 Bushwick Avenue, Brooklyn |
Brooklyn |
DCAS |
Building systems & Modifications |
|
Commented |
2018-10-15 |
| Installation of rooftop photovoltaic panels, Milton Fein School, 3201 Kingsbridge Avenue, Bronx |
Bronx |
DCAS |
Building systems & Modifications |
|
Commented |
2018-10-15 |
| Reconstruction of Corona Plaza, south side of Roosevelt Avenue between National Street and 104th Street, Queens |
Queens |
DDC |
Landscape architecture |
|
Commented |
2018-10-15 |
| Construction of two plazas, 37th Road, 73rd Street and Broadway, Queens |
Queens |
DDC |
Landscape architecture |
|
Commented |
2018-10-15 |
| Installation of rooftop photovoltaic panels, P.S. 214 Michael Friedsam, 2944 Pitkin Avenue, Brooklyn |
Brooklyn |
DCAS |
Building systems & Modifications |
|
Commented |
2018-10-15 |
| Update on DOT's guidelines for the siting and design of permanent sidewalk planters citywide |
Citywide |
DOT |
Street furniture |
|
Commented |
2018-10-15 |
| Installation of rooftop photovoltaic panels, P.S. 221, 791 Empire Boulevard, Brooklyn |
Brooklyn |
DCAS |
Building systems & Modifications |
|
Commented |
2018-10-15 |
| Construction of a comfort station, M. Fidler Wyckoff House Park, 5914 Clarendon Road, Brooklyn |
Brooklyn |
DPR |
Architecture |
|
Commented |
2018-10-15 |
| Installation of rooftop photovoltaic panels, P.S. 235, 525 Lenox Road, Brooklyn |
Brooklyn |
DCAS |
Building systems & Modifications |
|
Commented |
2018-10-15 |
| Installation of a prototypical neighborhood wayfinding (WalkNYC) sign, Stanley Isaacs Playground, East 96th Street and the FDR Drive, Manhattan |
Manhattan |
DOT |
Street furniture |
Preliminary and Final |
Approved |
2018-10-15 |
| Construction of athletic courts and installation of an artificial turf field, Surf Playground, adjacent to P.S. 288, Surf Avenue between West 27th Street and West 25th Street, Brooklyn |
Brooklyn |
DPR |
Landscape architecture |
Preliminary and Final |
Approved |
2018-10-15 |
| Construction of High Line Park (formerly elevated rail line), Phase IV, West 30th Street between 10th Avenue and 11th Avenue, Manhattan |
Manhattan |
DPR |
Landscape architecture |
|
Commented |
2018-10-15 |
| Construction of a dog run, Devoe Park, Sedgwick Avenue and West Fordham Road, Bronx |
Bronx |
DPR |
Landscape architecture |
Preliminary |
Approved |
2018-10-15 |
| Construction of a skate park, Harold Ickes Playground, Hamilton Avenue and Van Brunt Street, Brooklyn |
Brooklyn |
DPR |
Landscape architecture |
Final |
Approved |
2018-10-15 |
| Reconstruction of a parking lot and installation of a water tank, FDNY Fire Training Academy, Randall’s Island, Manhattan |
Manhattan |
FDNY |
Landscape architecture |
Preliminary |
Approved |
2018-10-15 |
| Installation of streetscape improvements, Water Street between Whitehall Street and Hanover Square, Manhattan |
Manhattan |
EDC |
Landscape architecture |
Final |
Approved |
2018-10-15 |
| Installation of roll-up doors and sales booth, 410 Halleck Street, east side of Hunts Point Produce Market Row B, Units 266-268, Bronx |
Bronx |
EDC |
Building systems & Modifications |
Preliminary and Final |
Approved |
2018-10-15 |
| Construction of boardwalk access ramps, Rockaway Beach, Rockaway Beach between Beach 24th Street and Beach 25th Street, Far Rockaway, Queens |
Queens |
DPR |
Landscape architecture |
Preliminary |
Approved with conditions |
2018-10-15 |
| Reconstruction of the playground, Beach 59th Street Playground, Rockaway Beach, Shore Front Parkway between Beach 59th Street and Beach 60th Street, Arverne, Queens |
Queens |
DPR |
Landscape architecture |
Preliminary |
Approved with conditions |
2018-10-15 |
| Construction of sand volleyball courts, an adult fitness area, lawn, and seating areas, Rockaway Beach, Shore Front Parkway between Beach 77th Street and Beach 81st Street, Arverne, Queens |
Queens |
DPR |
Landscape architecture |
Preliminary |
Approved with conditions |
2018-10-15 |
| Construction of a dog run, Rockaway Beach, Shore Front Parkway and Beach 90th Street, Far Rockaway, Queens |
Queens |
DPR |
Landscape architecture |
Preliminary |
Approved with conditions |
2018-10-15 |
| Installation of rooftop photovoltaic panels, P.S. 45 John Tyler, 58 Lawrence Avenue, Staten Island |
Staten Island |
DCAS |
Building systems & Modifications |
|
Commented |
2018-10-15 |
| Construction of a labyrinth plaza, paths, and lawn areas, Rockaway Beach, Shore Front Parkway between Beach 92nd Street and Beach 94th Street, Far Rockaway, Queens |
Queens |
DPR |
Landscape architecture |
Preliminary |
Approved with conditions |
2018-10-15 |
| Construction of Beach 98th Street Playground, Rockaway Beach, Shore Front Parkway between Beach 98th Street and Beach 101st Street, Rockaway Park, Queens |
Queens |
DPR |
Landscape architecture |
Preliminary |
Approved with conditions |
2018-10-15 |
| Construction of an adult fitness course and a pickleball court, Rockaway Beach, Shore Front Parkway between Beach 101st Street and Beach 102nd Street, Rockaway Park, Queens |
Queens |
DPR |
Landscape architecture |
Preliminary |
Approved with conditions |
2018-10-15 |
| Construction of an educational compost facility and adjacent site work, Queens Botanical Garden, 43-50 Main Street, Flushing, Queens |
Queens |
DPR |
Architecture |
Final |
Approved with conditions |
2018-10-15 |
| Construction of an adult fitness area, Flushing Meadows Corona Park, Corona Avenue and 111th Street, Corona, Queens |
Queens |
DPR |
Landscape architecture |
Preliminary |
Approved |
2018-10-15 |
| Rehabilitation of a dog run, Washington Park, Fourth Street, Fifth Avenue, Fifth Street, and Fourth Avenue, Brooklyn |
Brooklyn |
DPR |
Landscape architecture |
Final |
Approved |
2018-10-15 |
| Installation of windows, a door, and mechanical equipment, Owen F. Dolen Golden Age Recreation Center, Owen F. Dolen Park, 2551 Westchester Avenue, Bronx |
Bronx |
DPR |
Building systems & Modifications |
Preliminary |
Approved |
2018-10-15 |
| Reconstruction of staircase landings, the Prison Ship Martyrs Monument, Fort Greene Park, Myrtle Avenue, Washington Park, Dekalb Avenue and Saint Edward Street, Brooklyn |
Brooklyn |
DPR |
Artwork |
Preliminary and Final |
Approved |
2018-10-15 |
| Reconstruction of Penn Triangle, Wythe Avenue, Penn Street, and Williamsburg Street East, Brooklyn |
Brooklyn |
DPR |
Landscape architecture |
Final |
Approved |
2018-10-15 |
| Construction of a primary electrical substation, Oakwood Beach Water Pollution Control Plant, 751 Mill Road, Staten Island |
Staten Island |
DEP |
Architecture |
|
Commented |
2018-09-17 |
| Installation of a distinctive sidewalk, 156 Leroy Street, Manhattan |
Manhattan |
DOT |
Distinctive sidewalk |
|
Found incomplete |
2018-09-17 |
| Installation of a fence and related site work, John DeLury Square, Fulton Street and Gold Street, Manhattan |
Manhattan |
DPR |
Landscape architecture |
Preliminary |
Approved |
2018-09-17 |
| Construction of an upland park, including a playground and a prototypical comfort station, as Phase 1B of the reconstruction of Pier 42, East River Waterfront between Montgomery Street and Jackson Street, Manhattan |
Manhattan |
EDC |
Landscape architecture |
Preliminary |
Approved with conditions |
2018-09-17 |
| Installation of a door and retail signage (Big Eye Sushi), 2 Metrotech Center, Brooklyn |
Brooklyn |
EDC |
Signage |
Preliminary and Final |
Approved |
2018-09-17 |
| Reconstruction of Middle Playground and basketball courts, Morningside Park, Morningside Avenue between West 117th Street and West 119th Street, Manhattan |
Manhattan |
DPR |
Landscape architecture |
Final |
Approved |
2018-09-17 |
| Reconstruction of Lewis Playground, Willoughby Avenue and Lewis Avenue, Brooklyn |
Brooklyn |
DPR |
Landscape architecture |
Final |
Approved |
2018-09-17 |
| Reconstruction of Bill Bojangles Robinson Playground, West 150th Street and Seventh Avenue, Manhattan |
Manhattan |
DPR |
Landscape architecture |
Final |
Approved |
2018-09-17 |
| Reconstruction of a plaza, Doughboy Park, Woodside Avenue and 56th Street, Woodside, Queens |
Queens |
DPR |
Landscape architecture |
Final |
Approved |
2018-09-17 |
| Reconstruction of a dog run, Corlears Hook Park, Cherry Street, Jackson Street, and the FDR Drive, Manhattan |
Manhattan |
DPR |
Landscape architecture |
Final |
Approved |
2018-09-17 |
| Construction of an adult fitness area, Haggerty Park, Jamaica Avenue between 202nd Street and 204th Street, Hollis, Queens |
Queens |
DPR |
Landscape architecture |
Final |
Approved |
2018-09-17 |
| Construction of an adult fitness area, Albert Montbellier Park, 139th Avenue, Springfield Boulevard, Sloan Street and East Gate Plaza, Springfield Gardens, Queens |
Queens |
DPR |
Landscape architecture |
Final |
Approved |
2018-09-17 |
| Reconstruction of Playground One, adjacent to P.S. 1, Oliver Street, Madison Street, and Catherine Street, Manhattan |
Manhattan |
DPR |
Landscape architecture |
Preliminary and Final |
Approved |
2018-09-17 |