Repair and painting of the perimeter fence, Wards Island Wastewater Treatment Plant, Manhattan
Manhattan · DEP · Building systems & Modifications · Final · Commented
- Construction
- Rehabilitation
- Public/Private
- Public
- First Seen
- 2018-10-15
- Last Seen
- 2018-10-15
Stage Progression
Conceptual
—
Preliminary
2015-10-26
Final
2015-10-26
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2018-10-15 | Commented | annual_report_api | Minutes |
Related Projects
Same project, different review stage (1)
| Title | Stage | First Seen | Last Seen |
|---|---|---|---|
| Repair and painting of the perimeter fence, Wards Island Wastewater Treatment Pl… |
Other projects at this site (2)
| Title | Stage | Agency | First Seen |
|---|---|---|---|
| Construction of a prefabricated storage building, Wards Island Wastewater Treatm… | |||
| Construction of a prefabricated storage building, Wards Island Wastewater Treatm… | DEP | 2019-09-16 |