Construction of a parking lot, perimeter wall and fencing and adjacent site work as Phase I of the of the construction of an NYPD vehicle impound facility, Rockaway Boulevard, Guy Brewer Boulevard, Farmers Boulevard, JFK International Airport, Queens
Queens · EDC · Landscape architecture · Commented
- Construction
- Construction
- Public/Private
- Public
- First Seen
- 2018-04-16
- Last Seen
- 2018-07-09
Stage Progression
Conceptual
—
Preliminary
—
Final
—
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2018-04-16 | Commented | annual_report_api | Minutes | |||
| 2018-05-14 | Commented | annual_report_api | Minutes | |||
| 2018-06-11 | Commented | annual_report_api | Minutes | |||
| 2018-07-09 | Commented | annual_report_api | Minutes |