Construction of a primary electrical substation, Oakwood Beach Water Pollution Control Plant, 751 Mill Road, Staten Island
Staten Island · DEP · Architecture · Final · Commented
- Construction
- Construction
- Public/Private
- Public
- First Seen
- 2017-09-18
- Last Seen
- 2018-09-17
Stage Progression
Conceptual
—
Preliminary
2006-09-13
Final
2007-07-16
Result: Commented
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2017-09-18 | Commented | annual_report_api | Minutes | |||
| 2018-09-17 | Commented | annual_report_api | Minutes |
Related Projects
Same project, different review stage (2)
| Title | Stage | First Seen | Last Seen |
|---|---|---|---|
| Construction of a primary electrical substation, Oakwood Beach Water Pollution C… | |||
| Construction of a primary electrical substation, Oakwood Beach Water Pollution C… |
Other projects at this site (6)
| Title | Stage | Agency | First Seen |
|---|---|---|---|
| Installation of a rooftop chiller and gas meter assembly, Oakwood Beach Water Po… | |||
| Installation of doors and rooftop equipment, Oakwood Beach Water Pollution Contr… | DEP | 2017-05-22 | |
| Construction of an electrical building and adjacent site work, Oakwood Beach Wat… | DEP | 2017-06-19 | |
| Construction of a dechlorination facility, Oakwood Beach Water Pollution Control… | DEP | 2018-09-17 | |
| Construction of a dechlorination facility, Oakwood Beach Water Pollution Control… | Preliminary and Final | DEP | 2019-04-15 |
| Construction of an electrical building and adjacent site work, Oakwood Beach Wat… | Amended Final | DEP | 2025-03-24 |