Installation of ADA door actuators, Brooklyn Supreme Court, 360 Adams Street, Brooklyn

Brooklyn · DCAS · Building systems & Modifications · Final · Approved per delegation

Construction
Installation of specific elements
Public/Private
Public
Review Cycles
1
First Seen
2024-10-25
Last Seen
2024-11-18

Stage Progression

Conceptual
Preliminary
2024-10-25
Final
2024-10-25
Result: Approved per delegation

Review History

DateCertificateStageActionResultSourceDocs
2024-10-25 29002 Preliminary and Final Delegation Approval monthly_review_api
2024-11-18 Approved per delegation annual_report_api Minutes

Meeting Videos

Public Design Commission Meeting, Monday, November 18, 2024 (2024-11-18)

Related Projects

Other projects at this site (2)
TitleStageAgencyFirst Seen
Installation of a rooftop emergency generator and switchgear, Brooklyn Supreme C… Preliminary and Final DDC 2018-07-09
Rehabilitation of the façade and installation of guardrails, Brooklyn Supreme Co… Preliminary and Final DDC 2024-10-02