Installation of a rooftop emergency generator and switchgear, Brooklyn Supreme Court, 360 Adams Street, Brooklyn
Brooklyn · DDC · Building systems & Modifications · Final · Commented
- City Council
- 33
- Community Board
- 2
- Construction
- Installation of specific elements
- Public/Private
- Public
- Review Cycles
- 1
- First Seen
- 2018-07-09
- Last Seen
- 2023-02-13
Stage Progression
Conceptual
—
Preliminary
2018-07-09
Final
2018-07-09
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2018-07-09 | 26675 | Preliminary and Final | agenda_pdf | Minutes | ||
| 2018-07-09 | Approved | annual_report_api | Minutes | |||
| 2018-07-09 | 26675 | Preliminary and Final | Calendared for Consent | monthly_review_api | Minutes | |
| 2023-02-13 | Commented | annual_report_api | Minutes |
Meeting Videos
Related Projects
Other projects at this site (2)
| Title | Stage | Agency | First Seen |
|---|---|---|---|
| Rehabilitation of the façade and installation of guardrails, Brooklyn Supreme Co… | Preliminary and Final | DDC | 2024-10-02 |
| Installation of ADA door actuators, Brooklyn Supreme Court, 360 Adams Street, Br… | Preliminary and Final | DCAS | 2024-10-25 |