Installation of signage as part of the construction of a maintenance building, as Phase II (Southern Phase) of the construction of a waterfront park and streetscape improvements, Thompson Street, Wave Street and Bay Street, Stapleton, Staten Island
Staten Island · EDC · Signage · Approved per delegation
- Construction
- Installation of specific elements
- Public/Private
- Public
- Review Cycles
- 1
- First Seen
- 2024-08-23
- Last Seen
- 2024-09-16
Stage Progression
Conceptual
—
Preliminary
—
Final
2024-08-23
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2024-08-23 | 28938 | Amended Final | Delegation Approval | monthly_review_api | ||
| 2024-09-16 | Approved per delegation | annual_report_api | Minutes |