Construction of an addition to the Return and Waste Sludge Building and rehabilitation of the Final Settling Tanks, Owls Head Wastewater Resource Recovery Facility, 6700 Shore Road, Brooklyn
Brooklyn · DEP · Architecture · Final · Commented
- Construction
- Construction
- Public/Private
- Public
- First Seen
- 2023-12-11
- Last Seen
- 2023-12-11
Stage Progression
Conceptual
—
Preliminary
2025-10-21
Final
2025-10-21
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2023-12-11 | Commented | annual_report_api | Minutes |
Meeting Videos
Related Projects
Same project, different review stage (1)
| Title | Stage | First Seen | Last Seen |
|---|---|---|---|
| Construction of an addition to the Return and Waste Sludge Building and rehabili… | Preliminary and Final | 2025-10-21 | 2025-10-21 |
Other projects at this site (3)
| Title | Stage | Agency | First Seen |
|---|---|---|---|
| Installation of flood protection measures as part of the DEP Wastewater Resilien… | Preliminary and Final | DEP | 2019-07-15 |
| Construction of an electrical substation and adjacent site work, Owls Head Waste… | Final | DEP | 2025-03-24 |
| Renovation of the Chlorination Building, Owls Head Wastewater Resource Recovery … | Preliminary and Final | DEP | 2025-05-27 |