Construction of an addition to the Return and Waste Sludge Building and rehabilitation of the Final Settling Tanks, Owls Head Wastewater Resource Recovery Facility, 6700 Shore Road, Brooklyn

Brooklyn · DEP · Architecture · Final · Commented

Construction
Construction
Public/Private
Public
First Seen
2023-12-11
Last Seen
2023-12-11

Stage Progression

Conceptual
Preliminary
2025-10-21
Final
2025-10-21
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2023-12-11 Commented annual_report_api Minutes

Meeting Videos

Public Design Commission Meeting, December 11, 2023 (2023-12-11)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Construction of an addition to the Return and Waste Sludge Building and rehabili… Preliminary and Final 2025-10-21 2025-10-21
Other projects at this site (3)
TitleStageAgencyFirst Seen
Installation of flood protection measures as part of the DEP Wastewater Resilien… Preliminary and Final DEP 2019-07-15
Construction of an electrical substation and adjacent site work, Owls Head Waste… Final DEP 2025-03-24
Renovation of the Chlorination Building, Owls Head Wastewater Resource Recovery … Preliminary and Final DEP 2025-05-27