Minor modifications to the installation of a barge and gangway to accommodate citywide ferry service, 431 East 34th Street, between the FDR Drive and East River, Manhattan

Manhattan · EDC · Landscape Architecture · Final · Approved per delegation

Construction
Installation of specific elements
Public/Private
Public
Review Cycles
1
First Seen
2023-10-30
Last Seen
2023-11-13

Stage Progression

Conceptual
Preliminary
2023-10-30
Final
2023-10-30
Result: Approved per delegation

Review History

DateCertificateStageActionResultSourceDocs
2023-10-30 28627 Preliminary and Final Delegation Approval monthly_review_api
2023-11-13 Approved per delegation annual_report_api Minutes

Meeting Videos

Public Design Commission Meeting, November 13, 2023 (2023-11-13)

Related Projects

Modifications (1)
TitleStageFirst SeenResult
Installation of a barge and gangway to accommodate citywide ferry service, 431 E… Preliminary and Final 2018-04-16 Commented
Other projects at this site (1)
TitleStageAgencyFirst Seen
Modifications to the installation of a barge and gangway to accommodate citywide… Amended Final EDC/DOT 2026-02-23
Subscribe to Updates Back to Projects