Installation of a barge and gangway to accommodate citywide ferry service, 431 East 34th Street, between the FDR Drive and East River, Manhattan
Manhattan · EDC · Landscape architecture · Commented
- Construction
- Installation of specific elements
- Public/Private
- Public and Private
- Review Cycles
- 1
- First Seen
- 2018-04-16
- Last Seen
- 2023-01-17
Stage Progression
Conceptual
—
Preliminary
2018-04-16
Final
2018-04-16
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2018-04-16 | Approved | annual_report_api | Minutes | |||
| 2018-04-16 | 26566 | Preliminary and Final | Calendared for Consent | monthly_review_api | Minutes | |
| 2023-01-17 | Commented | annual_report_api | Minutes |