Construction of a tactical training facility and adjacent site work, Rodman’s Neck, Pelham Bay Park, Bronx

Bronx · DDC · Architecture · Final · Approved

Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2023-09-18
Last Seen
2023-09-18

Stage Progression

Conceptual
Preliminary
2022-06-13
Final
2023-09-18
Preliminary → Final: 462 days

Review History

DateCertificateStageActionResultSourceDocs
2023-09-18 Approved annual_report_api Minutes
2023-09-18 28582 Final Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Meeting, September 18, 2023 (2023-09-18)

Related Projects

Same project, different review stage (2)
TitleStageFirst SeenLast Seen
Construction of a tactical training facility and adjacent site work, Rodman’s Ne… 2021-11-15 2021-11-15
Construction of a tactical training facility and adjacent site work, Rodman’s Ne… Preliminary 2022-06-13 2022-06-13
Other projects at this site (2)
TitleStageAgencyFirst Seen
Installation of two prefabricated office trailers, Rodman’s Neck, Pelham Bay Par… Preliminary and Final DOC 2019-02-19
Installation of two prefabricated trailers and adjacent site work, Rodman’s Neck… Preliminary and Final DOC 2019-03-18