Construction of a tactical training facility and adjacent site work, Rodman’s Neck, Pelham Bay Park, Bronx

Bronx · DDC · Architecture · Final · Approved

City Council
13
Community Board
10
Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2022-06-13
Last Seen
2022-06-13

Stage Progression

Conceptual
Preliminary
2022-06-13
Final
2023-09-18
Preliminary → Final: 462 days

Review History

DateCertificateStageActionResultSourceDocs
2022-06-13 28128 Preliminary agenda_pdf Minutes
2022-06-13 Approved with conditions annual_report_api Minutes
2022-06-13 28128 Preliminary Calendared for Consent monthly_review_api Minutes

Related Projects

Same project, different review stage (2)
TitleStageFirst SeenLast Seen
Construction of a tactical training facility and adjacent site work, Rodman’s Ne… 2021-11-15 2021-11-15
Construction of a tactical training facility and adjacent site work, Rodman’s Ne… Final 2023-09-18 2023-09-18
Other projects at this site (2)
TitleStageAgencyFirst Seen
Installation of two prefabricated office trailers, Rodman’s Neck, Pelham Bay Par… Preliminary and Final DOC 2019-02-19
Installation of two prefabricated trailers and adjacent site work, Rodman’s Neck… Preliminary and Final DOC 2019-03-18