Rehabilitation of the Upper Effluent Chamber as part of the Kensico-Eastview Connection Project, Kensico Reservoir, 19 Westlake Drive, Mount Pleasant, Westchester County

Upstate · DEP · Architecture · Final · Approved

Construction
Rehabilitation
Public/Private
Public
First Seen
2021-09-20
Last Seen
2021-09-20

Stage Progression

Conceptual
Preliminary
2024-02-12
Final
2025-03-24
Preliminary → Final: 406 days

Review History

DateCertificateStageActionResultSourceDocs
2021-09-20 Commented annual_report_api Minutes

Related Projects

Same project, different review stage (2)
TitleStageFirst SeenLast Seen
Rehabilitation of the Upper Effluent Chamber as part of the Kensico-Eastview Con… Preliminary 2024-02-12 2024-02-12
Rehabilitation of the Upper Effluent Chamber as part of the Kensico-Eastview Con… Final 2025-03-24 2025-03-24
Other projects at this site (4)
TitleStageAgencyFirst Seen
Construction of a Waterfowl Management Program Building, Kensico Reservoir, 19 W… Preliminary DEP 2020-03-30
Rehabilitation of the former Kensico Laboratory, Kensico Reservoir, 19 Westlake … Preliminary DEP 2020-03-30
Construction of a Waterfowl Management Program Building, Kensico Reservoir, 19 W… Final DEP 2020-10-19
Rehabilitation of the former Kensico Laboratory, Kensico Reservoir, 19 Westlake … Final DEP 2020-11-16