Construction of a prototypical comfort station, Harlem River Park, Harlem River Drive, East 128th Street, and the Third Avenue Bridge, Manhattan

Manhattan · DPR · Architecture · Final · Approved

City Council
8 & 9
Community Board
11
Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2020-08-10
Last Seen
2020-08-10

Stage Progression

Conceptual
Preliminary
2020-01-21
Final
2020-08-10
Preliminary → Final: 202 days

Review History

DateCertificateStageActionResultSourceDocs
2020-08-10 27562 Final agenda_pdf Minutes
2020-08-10 Approved with conditions annual_report_api Minutes
2020-08-10 27562 Final Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Meeting Agenda Monday, August 10, 2020 (2020-08-10)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Construction of a prototypical comfort station, Harlem River Park, Harlem River … Preliminary 2020-01-21 2020-01-21
Subscribe to Updates Back to Projects