Installation of flood protection measures as a part of the DEP Wastewater Resiliency Program, Roosevelt Island Main Pump Station, 728 Main Street, Roosevelt Island, Manhattan

Manhattan · DEP · Building systems & Modifications · Approved

City Council
5
Community Board
8
Construction
Installation of specific elements
Public/Private
Public
Review Cycles
1
First Seen
2020-04-20
Last Seen
2020-04-20

Stage Progression

Conceptual
Preliminary
2020-04-20
Final
2020-04-20

Review History

DateCertificateStageActionResultSourceDocs
2020-04-20 27440 Preliminary and Final agenda_pdf Minutes
2020-04-20 Approved annual_report_api Minutes
2020-04-20 27440 Preliminary and Final Calendared for Consent monthly_review_api Minutes

Meeting Videos