Reconstruction of Roberto Clemente Plaza, Third Avenue, East 147th Street, East 149th Street and Willis Avenue, Bronx

Bronx · DDC · Landscape architecture · Final · Commented

Construction
Reconstruction
Public/Private
Public
First Seen
2017-09-18
Last Seen
2017-09-18

Stage Progression

Conceptual
Preliminary
2011-07-18
Final
2012-05-14
Preliminary → Final: 301 days
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2017-09-18 Commented annual_report_api Minutes