Installation of aeration tank mixer platforms, piping, conduit, louvers and lighting as part of a Level 1 Biological Nutrient Removal Upgrade, Coney Island Wastewater Treatment Plant, 2591 Knapp Street, Brooklyn

Brooklyn · DEP · Architecture · Commented

Construction
Installation of specific elements
Public/Private
Public
First Seen
2019-01-22
Last Seen
2023-03-20

Stage Progression

Conceptual
Preliminary
Final

Review History

DateCertificateStageActionResultSourceDocs
2019-01-22 Commented annual_report_api Minutes
2023-03-20 Commented annual_report_api Minutes

Meeting Videos

Public Design Commission Public Meeting, Monday, March 20, 2023 (2023-03-20)