Reconstruction of DeMatti Playground, Tompkins Avenue between Chestnut Avenue and Shaughnessy Lane, Staten Island

Staten Island · DPR · Landscape architecture · Final · Commented

Construction
Reconstruction
Public/Private
Public
First Seen
2018-09-17
Last Seen
2020-10-19

Stage Progression

Conceptual
Preliminary
2015-06-22
Final
2016-01-11
Preliminary → Final: 203 days
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2018-09-17 Found incomplete annual_report_api Minutes
2020-10-19 Commented annual_report_api Minutes