Stabilization of the shoreline adjacent to Shaft 18, Kensico Reservoir, Westlake Drive, Valhalla, Mount Pleasant, Westchester County

Unknown Borough · Unknown Agency · · Final · Commented

First Seen
N/A
Last Seen
N/A

Stage Progression

Conceptual
Preliminary
2015-12-07
Final
2016-10-17
Preliminary → Final: 315 days
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2016-10-17 25915 Final agenda_pdf Minutes

Related Projects

Same project, different review stage (2)
TitleStageFirst SeenLast Seen
Stabilization of the shoreline adjacent to Shaft 18, Kensico Reservoir, Westlake…
Stabilization of the shoreline adjacent to Shaft 18, Kensico Reservoir, Westlake… 2018-03-12 2024-06-18
Subscribe to Updates Back to Projects