Installation of an ADA ramp and adjacent site work, 80 Centre Street, Manhattan

Unknown Borough · Unknown Agency · · Final · Approved

City Council
1
Community Board
1
First Seen
N/A
Last Seen
N/A

Stage Progression

Conceptual
Preliminary
2015-11-16
Final
2021-10-18
Preliminary → Final: 2163 days

Review History

DateCertificateStageActionResultSourceDocs
2015-11-16 25565 Preliminary agenda_pdf Minutes
2015-12-07 25565 Preliminary agenda_pdf Minutes
2016-01-11 25565 Preliminary agenda_pdf Minutes

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Installation of an ADA ramp and adjacent site work, 80 Centre Street, Manhattan Final 2021-10-18 2021-10-18
Other projects at this site (2)
TitleStageAgencyFirst Seen
Installation of louvers, 80 Centre Street, Manhattan
Minor modifications to the installation of an ADA ramp and adjacent site work, 8… Amended Final DDC/DOT 2025-12-01