Construction of a biogas conditioning system and adjacent site work, Newtown Creek Water Pollution Control Plant, 329 Greenpoint Avenue, Brooklyn
Unknown Borough · Unknown Agency · · Preliminary
- City Council
- 33
- Community Board
- 1
- First Seen
- N/A
- Last Seen
- N/A
Stage Progression
Conceptual
—
Preliminary
2015-04-20
Final
—
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2015-04-20 | 25327 | Preliminary | agenda_pdf |
Related Projects
Same project, different review stage (1)
| Title | Stage | First Seen | Last Seen |
|---|---|---|---|
| Construction of a biogas conditioning system and adjacent site work, Newtown Cre… |
Other projects at this site (1)
| Title | Stage | Agency | First Seen |
|---|---|---|---|
| Construction of a chlorine contact tank enclosure and a final effluent enclosure… | DEP | 2017-08-14 |