Installation of sub-slab depressurization system, Manhattan Center for Science and Mathematics (formerly Benjamin Franklin High School), 260 Pleasant Avenue, Manhattan

Unknown Borough · Unknown Agency · · Final · Commented

City Council
8
Community Board
11
First Seen
N/A
Last Seen
N/A

Stage Progression

Conceptual
Preliminary
2011-12-12
Final
2014-03-10
Preliminary → Final: 819 days
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2014-03-10 24978 Final agenda_pdf