Construction of a total residual chlorine reduction building, Coney Island Wastewater Resource Recovery Facility, 2591 Knapp Street, Brooklyn
Brooklyn · DEP · Architecture · Commented
- Construction
- Construction
- Public/Private
- Public
- First Seen
- 2022-06-13
- Last Seen
- 2022-06-13
Stage Progression
Conceptual
—
Preliminary
—
Final
—
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2022-06-13 | Commented | annual_report_api | Minutes |
Related Projects
Other projects at this site (1)
| Title | Stage | Agency | First Seen |
|---|---|---|---|
| Installation of a conduit support structure, Coney Island Wastewater Resource Re… | Preliminary and Final | DEP | 2019-12-16 |