Construction of an entrance building, Shaft 4, Catskill Aqueduct and Delaware Aqueduct interconnection, Route 208 and Armato Lane, Gardiner, Ulster County
Upstate · DEP · Architecture · Final · Commented
- Construction
- Construction
- Public/Private
- Public
- First Seen
- 2019-06-17
- Last Seen
- 2019-06-17
Stage Progression
Conceptual
—
Preliminary
2012-04-02
Final
2012-04-02
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2019-06-17 | Commented | annual_report_api | Minutes |
Related Projects
Same project, different review stage (1)
| Title | Stage | First Seen | Last Seen |
|---|---|---|---|
| Construction of an entrance building, Shaft 4, Catskill Aqueduct and Delaware Aq… |