Reconstruction of Summit Playground, Macombs Dam Park, Summit Avenue and West 161st Street, Bronx

Bronx · DPR · Landscape architecture · Final · Approved with conditions

Public/Private
Public
First Seen
2025-05-27
Last Seen
2025-05-27

Stage Progression

Conceptual
Preliminary
2024-11-18
Final
2025-05-27
Preliminary → Final: 190 days
Result: Approved with conditions

Review History

DateCertificateStageActionResultSourceDocs
2025-05-27 30024 Final Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Meeting, Tuesday, May 27, 2025 (2025-05-27)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Reconstruction of Summit Playground, Macombs Dam Park, Summit Avenue and West 16… Preliminary 2024-11-18 2024-11-18