Reconstruction of a multipurpose play area and playground and construction of a dog run as Phase III of the reconstruction of Commodore Barry Park, Flushing Avenue, North Elliot Place, Park Avenue, and Navy Street, Brooklyn

Brooklyn · DPR · Landscape architecture · Final · Approved with conditions

Public/Private
Public
First Seen
2025-02-24
Last Seen
2025-02-24

Stage Progression

Conceptual
Preliminary
2024-02-12
Final
2025-02-24
Preliminary → Final: 378 days
Result: Approved with conditions

Review History

DateCertificateStageActionResultSourceDocs
2025-02-24 29915 Final Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Meeting, Monday, February 24, 2025 (2025-02-24)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Reconstruction of a multipurpose play area and playground and construction of a … 2024-02-12 2024-02-12
Other projects at this site (4)
TitleStageAgencyFirst Seen
Reconstruction of a multipurpose field and adjacent site work as Phase II of the… Preliminary DPR 2019-07-15
Design of a master plan for Commodore Barry Park, Flushing Avenue, North Elliot … DPR 2019-07-15
Reconstruction of a multipurpose field and adjacent site work as Phase II of the… Final DPR 2020-01-21
Minor modifications to the reconstruction of a multipurpose field and adjacent s… Amended Final DPR 2024-06-02