Minor modifications to the fencing as part of the reconstruction of the coastline (East Side Coastal Resiliency) and East River Park, including the construction of three bridges, a comfort station, two recreation centers, and two gate houses, East River between Montgomery Street and East 25th Street, Manhattan
Manhattan · DDC/DPR/DOT · Landscape architecture · Final
- Public/Private
- Public
- First Seen
- 2025-01-21
- Last Seen
- 2025-01-21
Stage Progression
Conceptual
—
Preliminary
—
Final
2025-01-21
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2025-01-21 | 29868 | Amended Final | Calendared for Consent | monthly_review_api | Minutes |
Meeting Videos
Related Projects
Modifications (1)
| Title | Stage | First Seen | Result |
|---|---|---|---|
| Reconstruction of the coastline (East Side Coastal Resiliency) and East River Pa… | Preliminary | 2019-09-16 | Commented |
Other projects at this site (6)
| Title | Stage | Agency | First Seen |
|---|---|---|---|
| Reconstruction of the coastline (East Side Coastal Resiliency) and East River Pa… | Final | DDC | 2020-01-21 |
| Minor shifting of floodwall alignment as part of the reconstruction of the coast… | Amended Final | DDC | 2023-01-17 |
| Reconstruction of the coastline (East Side Coastal Resiliency) and East River Pa… | DDC | 2023-03-20 | |
| Minor modifications to the paving as part of the reconstruction of the coastline… | Amended Final | DDC | 2024-10-15 |
| Installation of vents as part of the reconstruction of the coastline (East Side … | Amended Final | DDC/DPR/DOT | 2025-02-24 |
| Minor modifications to the paving as part of the reconstruction of the coastline… | Amended Final | DDC/EDC | 2025-04-28 |