Minor modifications to the reconstruction of a salt shed and interim compost facility as a part of the Gowanus Canal combined sewer overflow (CSO) facility, 2nd Avenue and 6th Street, Brooklyn
Brooklyn · DEP · Architecture · Final · Approved per delegation
- Construction
- Reconstruction
- Public/Private
- Public
- Review Cycles
- 1
- First Seen
- 2024-07-26
- Last Seen
- 2024-08-12
Stage Progression
Conceptual
—
Preliminary
—
Final
2024-07-26
Review History
| Date | Certificate | Stage | Action | Result | Source | Docs |
|---|---|---|---|---|---|---|
| 2024-07-26 | 28899 | Amended Final | Delegation Approval | monthly_review_api | Minutes | |
| 2024-08-12 | Approved per delegation | annual_report_api |
Meeting Videos
Related Projects
Modifications (1)
| Title | Stage | First Seen | Result |
|---|---|---|---|
| Reconstruction of a salt shed and interim compost facility as part of the Gowanu… | 2022-03-14 | Commented |
Other projects at this site (1)
| Title | Stage | Agency | First Seen |
|---|---|---|---|
| Reconstruction of a salt shed and interim compost facility as part of the Gowanu… | Preliminary and Final | DEP | 2022-07-11 |