Construction of an ADA path and adjacent site work, Givans Creek Woods, Co-op City Boulevard between Baychester Avenue and Dreiser Loop, Bronx

Bronx · DPR · Landscape architecture · Final · Approved

City Council
12
Community Board
10
Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2024-07-15
Last Seen
2024-07-15

Stage Progression

Conceptual
Preliminary
2024-07-15
Final
2025-07-21
Preliminary → Final: 371 days

Review History

DateCertificateStageActionResultSourceDocs
2024-07-15 28889 Preliminary agenda_pdf Minutes
2024-07-15 Approved annual_report_api Minutes
2024-07-15 28889 Preliminary Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Meeting, Monday, July 15, 2024 (2024-07-15)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Construction of an ADA path and adjacent site work, Givans Creek Woods, Co-op Ci… Final 2025-07-21 2025-07-21