Reconstruction of a storefront, as part of Phase II of the construction of CityPoint, 445 Albee Square West, Brooklyn

Brooklyn · EDC · Architecture · Final · Approved

City Council
33
Community Board
2
Construction
Reconstruction
Public/Private
Public and Private
Review Cycles
1
First Seen
2024-02-12
Last Seen
2024-02-12

Stage Progression

Conceptual
Preliminary
2024-02-12
Final
2024-08-12
Preliminary → Final: 182 days

Review History

DateCertificateStageActionResultSourceDocs
2024-02-12 28735 Preliminary agenda_pdf Minutes
2024-02-12 Approved with conditions annual_report_api Minutes
2024-02-12 28735 Preliminary Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Meeting, Monday, February 12, 2024 (2024-02-12)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Reconstruction of a storefront, as part of Phase II of the construction of CityP… Final 2024-09-16 2024-09-16