Design of prototypical pipe bollards for installation citywide

Citywide · DOT · Street furniture · Final · Approved

Public/Private
Public
First Seen
2022-11-21
Last Seen
2022-11-21

Stage Progression

Conceptual
Preliminary
2021-02-22
Final
2022-11-21
Preliminary → Final: 637 days

Review History

DateCertificateStageActionResultSourceDocs
2022-11-21 28299 Amended Final Delegation Approval monthly_review_api

Related Projects

Same project, different review stage (2)
TitleStageFirst SeenLast Seen
Design of prototypical pipe bollards for installation citywide Preliminary and Final 2021-02-22 2022-12-12
Design of prototypical pipe bollards for installation citywide Amended Final 2024-09-16 2024-09-16