Removal and replacement of a cooling tower, Queens Central Library, 89-11 Merrick Boulevard, Jamaica, Queens

Queens · QPL · Building systems & Modifications · Final · Approved per delegation

Construction
Installation of specific elements
Public/Private
Public
Review Cycles
1
First Seen
2024-01-26
Last Seen
2024-02-12

Stage Progression

Conceptual
Preliminary
2024-01-26
Final
2024-01-26
Result: Approved per delegation

Review History

DateCertificateStageActionResultSourceDocs
2024-01-26 28715 Preliminary and Final Delegation Approval monthly_review_api
2024-02-12 Approved per delegation annual_report_api Minutes

Meeting Videos

Public Design Commission Meeting, Monday, February 12, 2024 (2024-02-12)

Related Projects

Other projects at this site (3)
TitleStageAgencyFirst Seen
Installation of rooftop equipment, Queens Central Library, 89-11 Merrick Bouleva… QPL 2017-02-13
Replacement of rooftop mechanical equipment, Queens Central Library, 89-11 Merri… Preliminary and Final QPL 2025-04-07
Minor modifications to the replacement of rooftop mechanical equipment, Queens C… Amended Final QPL 2025-06-06
Subscribe to Updates Back to Projects