Construction of an ADA path and adjacent site work, Great Hill, Central Park, Central Park West between West 103rd Street and West 107th Street, Manhattan

Manhattan · DPR · Landscape architecture · Final · Approved

Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2023-11-13
Last Seen
2023-11-13

Stage Progression

Conceptual
Preliminary
2023-11-13
Final
2023-12-11
Preliminary → Final: 28 days

Review History

DateCertificateStageActionResultSourceDocs
2023-11-13 Approved annual_report_api Minutes
2023-11-13 28657 Preliminary Calendared for Public Hearing monthly_review_api Minutes

Meeting Videos

Public Design Commission Meeting, November 13, 2023 (2023-11-13)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Construction of an ADA path and adjacent site work, Great Hill, Central Park, Ce… Final 2023-12-11 2023-12-11