Construction of Thames Plaza, including installation of security gates and bollards, Thames Street between Trinity Place and Broadway, Manhattan

Manhattan · DOT · Landscape Architecture · Final · Approved

Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2023-11-13
Last Seen
2023-11-13

Stage Progression

Conceptual
Preliminary
2023-07-17
Final
2023-11-13
Preliminary → Final: 119 days