Construction of a retaining wall, J. Hood Wright Park, South Pinehurst Avenue and West 176th Street, Manhattan

Manhattan · DPR · Landscape Architecture · Final · Approved

Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2023-11-13
Last Seen
2023-11-13

Stage Progression

Conceptual
Preliminary
2023-09-18
Final
2023-11-13
Preliminary → Final: 56 days

Review History

DateCertificateStageActionResultSourceDocs
2023-11-13 Approved annual_report_api Minutes
2023-11-13 28641 Final Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Meeting, November 13, 2023 (2023-11-13)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Construction of a retaining wall, J. Hood Wright Park, South Pinehurst Avenue an… Preliminary 2023-09-18 2023-09-18
Subscribe to Updates Back to Projects