Installation of rooftop guardrails and replacement of the roof, Fort Washington Armory, 216 Fort Washington Avenue, Manhattan

Manhattan · DDC · Building systems & Modifications · Final · Approved per delegation

Construction
Installation of specific elements
Public/Private
Public
Review Cycles
1
First Seen
2023-10-30
Last Seen
2023-11-13

Stage Progression

Conceptual
Preliminary
2023-10-30
Final
2023-10-30
Result: Approved per delegation

Review History

DateCertificateStageActionResultSourceDocs
2023-10-30 28624 Preliminary and Final Delegation Approval monthly_review_api
2023-11-13 Approved per delegation annual_report_api Minutes

Meeting Videos

Public Design Commission Meeting, November 13, 2023 (2023-11-13)

Related Projects

Other projects at this site (5)
TitleStageAgencyFirst Seen
Installation of rooftop mechanical equipment, Fort Washington Armory, 216 Fort W…
Installation of rooftop mechanical equipment, Fort Washington Armory, 216 Fort W… DHS 2017-01-18
Installation of a door and louver, Fort Washington Armory, 216 Fort Washington A… Preliminary and Final DHS 2019-12-16
Installation of rooftop mechanical equipment, Fort Washington Armory, 216 Fort W… Preliminary and Final DDC 2024-08-23
Minor modifications to the installation of rooftop mechanical equipment, Fort Wa… Amended Final DDC/DHS 2025-07-18
Subscribe to Updates Back to Projects