Installation of prototypical pipe bollards at the construction of a prototypical planted median, Grand Concourse Boulevard, Phase IV, from East 175th Street to East Fordham Road, Bronx

Bronx · DOT · Landscape architecture · Final · Approved

Construction
Installation of specific elements
Public/Private
Public
Review Cycles
1
First Seen
2023-05-22
Last Seen
2023-05-22

Stage Progression

Conceptual
Preliminary
Final
2023-05-22

Review History

DateCertificateStageActionResultSourceDocs
2023-05-22 Approved annual_report_api Minutes
2023-05-22 28501 Amended Final Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Meeting, May 22, 2023 (2023-05-22)

Related Projects

Other projects at this site (1)
TitleStageAgencyFirst Seen
Construction of a prototypical planted median, Grand Concourse Boulevard, Phase … Final DDC 2018-08-13