Modifications to a fence as part of the construction of a park, Willoughby Street, Duffield Street and Gold Street, Brooklyn

Brooklyn · EDC · Landscape architecture · Final · Approved with conditions

Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2023-03-20
Last Seen
2023-03-20

Stage Progression

Conceptual
Preliminary
Final
2023-03-20
Result: Approved with conditions

Review History

DateCertificateStageActionResultSourceDocs
2023-03-20 Approved with conditions annual_report_api Minutes
2023-03-20 28403 Amended Final Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Public Meeting, Monday, March 20, 2023 (2023-03-20)

Related Projects

Other projects at this site (7)
TitleStageAgencyFirst Seen
Construction of a park, Willoughby Street, Duffield Street and Gold Street, Broo…
Construction of a park, Willoughby Street, Duffield Street and Gold Street, Broo… EDC 2019-09-16
Installation of an interim open space, Willoughby Street, Duffield Street and Go… Preliminary and Final EDC 2020-07-13
Construction of a park, Willoughby Street, Duffield Street and Gold Street, Broo… EDC 2021-01-19
Removal of an interim seating area as part of the construction of a park (Abolit… Amended Final EDC 2022-12-12
Minor modifications to signage as part of the construction of a park (Abolitioni… Amended Final EDC 2023-05-22
Minor modifications to signage as part of the construction of a park (Abolitioni… Amended Final EDC 2023-09-18
Subscribe to Updates Back to Projects