Construction of stairs and a ramp, Bronx Park, Waring Avenue between Bronx River Parkway and Bronx Park East, Bronx

Bronx · DPR · Street furniture · Final · Approved

City Council
15
Community Board
11
Construction
Construction
Public/Private
Public
Review Cycles
1
First Seen
2022-11-07
Last Seen
2022-11-07

Stage Progression

Conceptual
Preliminary
2022-11-07
Final
2023-06-20
Preliminary → Final: 225 days

Review History

DateCertificateStageActionResultSourceDocs
2022-11-07 28278 Preliminary agenda_pdf Minutes
2022-11-07 Approved annual_report_api Minutes
2022-11-07 28278 Preliminary Calendared for Consent monthly_review_api Minutes

Meeting Videos

Public Design Commission Public Meeting, Monday, November 7, 2022 (2022-11-07)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Construction of stairs and a ramp, Bronx Park, Waring Avenue between Bronx River… Final 2023-06-20 2023-06-20