Installation of interim HVAC equipment, Manhattan Detention Complex, 100 Centre Street, Manhattan

Manhattan · DDC · Building systems & Modifications · Final · Commented

City Council
1
Community Board
1
Construction
Installation of specific elements
Public/Private
Public
Review Cycles
1
First Seen
2022-06-13
Last Seen
2024-03-18

Stage Progression

Conceptual
Preliminary
2022-06-13
Final
2022-06-13
Result: Commented

Review History

DateCertificateStageActionResultSourceDocs
2022-06-13 28127 Preliminary and Final agenda_pdf Minutes
2022-06-13 Approved annual_report_api Minutes
2022-06-13 28127 Preliminary and Final Calendared for Consent monthly_review_api Minutes
2024-03-18 Commented annual_report_api Minutes

Meeting Videos

Public Design Commission Meeting, Monday, March 18, 2024 (2024-03-18)

Related Projects

Other projects at this site (2)
TitleStageAgencyFirst Seen
Modifications to the installation of an interim sally port and bail payment cent…
Installation of an interim sally port and bail payment center, Manhattan Detenti… Preliminary and Final DDC 2022-04-11
Subscribe to Updates Back to Projects