Reconstruction of a pier, installation of a barge, gangway, and gate, and adjacent site work to accommodate citywide ferry service, Kaiser Park, between Bayview Avenue, West 29th Street, and Coney Island Creek, Brooklyn

Brooklyn · EDC · Landscape Architecture · Final · Approved with conditions

City Council
47
Community Board
13
Construction
Reconstruction
Public/Private
Public and Private
Review Cycles
1
First Seen
2021-04-26
Last Seen
2021-07-19

Stage Progression

Conceptual
Preliminary
2021-03-22
Final
2021-04-26
Preliminary → Final: 35 days
Result: Approved with conditions

Review History

DateCertificateStageActionResultSourceDocs
2021-04-26 27761 Final agenda_pdf Minutes
2021-04-26 Approved with conditions annual_report_api Minutes
2021-04-26 27761 Final Calendared for Consent monthly_review_api Minutes
2021-07-19 Commented annual_report_api Minutes

Meeting Videos

Public Design Commission Public Meeting, Monday, April 26, 2021 (2021-04-26)

Related Projects

Same project, different review stage (1)
TitleStageFirst SeenLast Seen
Reconstruction of a pier, installation of a barge, gangway, and gate, and adjace… Preliminary 2021-03-22 2021-03-22
Other projects at this site (1)
TitleStageAgencyFirst Seen
Patch and repair of a guardrail as part of the reconstruction of a pier, install… Amended Final EDC 2022-12-12
Subscribe to Updates Back to Projects